today i visited dha phase 6 after gap of3 months........... lotsss of work going on people going here and there but i was very surprised to see the pace of work the water tanks of sector B H A whihc should have been completed are still not complete......thought there is possesion of B H and A block cables are still being laid down............its total mess in these 3 block .......... there is still vilagge house in sector G and around whihc roads are being constructed........ in L block near the water tanks DHA has not managed to vacate the houses there too... its very surprising that in phase 6 whihc was balotted in 2003 still all land is not under possession of dha like in G and L bloack whihc is aw with my own eyes villager still living there.........................there seems to be some hurry now but i think it want be before 1 year that phase is live ble that too if work is accelerated ......................... though i have been big fan of DHA but this situation is very alarming.........there is still phase 5 and 7 to go then there is 8 and 9 10........... i will strongly advise ppl who want to make house not to by files............. GOD knows when will those phases be developed.........Brother CMY has said other phases will be statretd altogether and they wil be complte in5 7 years similar promises with banners were made about phase 6 too i saw banners by DHA in MAsjid chock in 2002 that phase 6 will be developed by international compnaies .. other than golf course i see local companies there working at very slow pace........... DHA is finding it very hard to complete even phase 6 in time i am not saying they canot do it but they are doin it very slowly considering much of land of phase 6 was litigation free............. how ever this want be case in phase8 and 9 10 where there is already rumours about litgation land......... and phase 8 area is densely populated..............if DHA has not managed to clear all area of phase 6 in 4 years how they plan to do it for phase7 8 9 and 10 ........as i say a bird in hand is better than two in sky ... so those who want to buy to build house in 5 years look in phase 6 only