Friends,
I recently visited D-12 and wanted interested parties to update you on what I saw.
1. Underground electric work was in full progress.I saw more then a dozen people working.
2. Sewege was previously completed for most area but I saw more pipes. I assume they were for the area that was illegally occupied earlier and now vacated.
3. A lot of yellow pipes were delivered that were not there just last month. Not sure what those yellow pipes are.
4. A lot of ground was dug for utilities that was not there just a month ago according to a local.
Therefore it appears that all utilities work are well underway and 'appears' to be promising. Hopefully the contractor is pushing to complete the work by April 2009 as agreed bewtween CDA and contractor.
Regards
Desi