Lahore ring road - southern loop approved,

(84573)
Friday, April 24, 2015 09:44 PM 

Good News:
The awaited project for many of the friends. Lahore ring road southern loop construction approved!

www.tribune.com.pk/story/875506/urban-planning-construction-of-3-packages-of-ring-road-approved/




LAHORE:

The Planning and Development Department on Friday approved the construction of three of the five packages of the Lahore Ring Road’s southern loop.

The decision was taken at the meeting of the steering committee of the P&D’s Public-Private Partnership Cell. The meeting was chaired by Finance Minister Mujtaba Shujaur Rehman.

It was decided that the Lahore Ring Road Authority would seek requests for proposals (RFP) from construction companies in two weeks.

With the revisions approved at the meeting, construction cost of the project would come down from Rs54 billion to Rs34 billion.

Financial plan

The meeting decided that the project would be undertaken in a build and transfer (BT) mode rather than the built, lease and transfer (BLT) mode approved earlier.

Under the BT mode, the ownership of the LRR southern loop would be transferred to the Lahore Ring Road Authority at the completion of its construction (in about two years).

The LRRA would now be responsible for the maintenance and operation (collection of toll tax).

This would save Rs29 billion earlier earmarked as a lump-sum payment to the construction company for maintenance.

Under the revised plan, the LRRA would pay back the construction cost in eight years at a 17-percent rate of interest.

Under the BLT mode, the ownership of the southern loop would have stayed with the construction company for 18 years after construction. The company would have leased the road to the government for toll tax collection.

Revised plan

The meeting also decided to construct service lanes on both sides of the road for only a five-kilometre stretch to bring down the construction cost from Rs54 billion to Rs35 billion.

Packages detail

Of the three packages of the southern loop approved on Friday, package 1 (9.35 kilometre) will connect the northern loop in Defence Housing Authority with Ferozpur Road; package 2 (13 km) will connect Ferozpur Road at Gajju Matta to Adda Plot; and package 3 (8km) will run from Adda Plot to Multan Road.

P&D PPP Cell Member Agha Waqar told The Express Tribune that revisions were undertaken to attract foreign investment.

Land acquisition

The P&D has so far released Rs9 billion to the LRRA for land acquisition.

An official who was present at the meeting says that the LRRA may need to pay another Rs12 billion for the purpose.

Published in The Express Tribune, April 25th, 2015.

Lahori_guy replied on Friday, April 24, 2015 10:38 PM 

The ring road southern loop approval news has been there for past 2-3 years. Let wait for shahbaz shareef to do the inauguration first to make sure it happens this time.

Khurram replied on Friday, April 24, 2015 11:11 PM 

Mujahid Bhai Good to see your comments from Chi-town. May Allah give strength to always correctly guide people for their welfare.

CMY replied on Friday, April 24, 2015 11:18 PM 

Aggar aap UK waley Khurram hein to bhai mien aap ko bohat miss karta hoon.

I met so many very great people here and you was one of them. I greatly miss all my old friends here like Abdul Raheem Hussain Kaisrani & Assad sahib sahib. If they are reading this post my Salam to all of you.

Choudry Mujahid Yasin ( CMY )
Info@LREPK.Com

ahmad replied on Saturday, April 25, 2015 12:54 AM 

dear cmy!i really appreciate the level of concern u have to update the the genral public/investers about the latest development in estate sector n inspired too with ur analytical strength to evaluate.one more question.......that at this time what purchases one can make with small capita to gain maximum on short term (6 month) basis.and what are those items,their present price and their future likely gains.tnx n regards.

gauhar-lahore replied on Saturday, April 25, 2015 04:45 AM 

dear CMY sb,AoA.
in all the above discussion there is no news about latest route(any change in route or old map as shown in LRE-map of Specially SL-3)
please comment.
regards.

Curious replied on Saturday, April 25, 2015 07:51 AM 

Does anyone know if the map for SL3 passing through Bahria remains the same as in the old map or has it changed?

Madris76 replied on Saturday, April 25, 2015 09:58 AM 

Dear CMY Sb,

Please inform your readers about the latest map of Ring Road SL-3 through your sources, whether it is with old route or there is any change.

Lahore Ring Road replied on Saturday, April 25, 2015 07:24 PM 

The CM said Lahore Ring Road Southern Loop project was of vital importance and there was a need for execution of that project speedily, adding construction of Northern Loop of Lahore Ring Road had resulted in better transport facilities to the citizens.

He said maintenance of a high standard, transparency and speedy execution of development projects was the hallmark of Punjab government and no compromise would be made on the construction of Southern Loop of Lahore Ring Road as well.

www.brecorder.com/business-a-economy/189/1149227/

Kashif ALi replied on Wednesday, April 29, 2015 10:38 AM 

Dear Choudry Mujahid Yasin ( CMY),

Please answer few of my queries

1. Based on the announcement of Southern Loop of Ring Road, what potential of investment you for see and in what societies?

2. Shall we wait for the revised map of Southern Loop of Ring Road before making any investment?

3. What future do you see of DHA Rahbar, NFC II and Sui Gas II as these societies have not shown enough potential in the past?

Looking forward for your usual analytical response.

Regards,
Kashif Ali
>