Work Details Rate Total Cost Remarks
Labour contractor charges   3,90,000 Your structure will be completed in 60 days
Ghasso   50,000.00 Earth filling
Steel {sarya} per ton ,000.00 "Model steel" Deformed 10 ton includes basement
Cement 334 272, bags
crush Margalla 46/sft 1,20,000 3 trucks Margalla crush
sand 8/sft 60, trolleys
Bricks 5.3 424,,000 bricks
Anti-termite   15,th generation formula
Electrician   20,000.00  
Electric items   170,000.00 Fast cables,Fans,lights,conduting,switches
Plumber   20,000.00  
Sanitary items   89,057.00 Turkish set
Sanitary fittings   82,820.00 Porta,Fasial
Bath tub   6,500.00  
Shower cabin   15,000.00  
Aluminum   150,000.00  
Grills   40,000.00  
Gate   40,000.00  
Terrace railing   30,500.00  
Spiral stairs till roof outside   28,000.00  
Inside SS railing   25,000.00  
Marble cost Botisena   88,790.00  
Flooring Tiles cost 24 inch size 950 24,st floor sitting, kitchen, patio -All imported
Bath tiles 704/ 81,800.00 Master "A" Class from show room
meter
Grinding   26,000.00  
Roof insulation tiles 22 22,000.00 Thermopore 2" thick
False ceiling   34,000.00  
Painter   34,732.00  
Paint/material   71,169.00 ICI factory price
Kitchen Marble slabs   10,000.00  
Kitchen wall tiles   7,000.00  
Main door “Black Gold” Marble Slabs/steps   6,000.00  
Wooden flooring 8mm   25,000.00 Malaysian imported
Carpenter labour charges   72,725.00  
Wooden doors material   79,750.00  
Kitchen wood material   35,680.00  
Elmira wood material   115,910.00  
Door locks   32,290.00 Tower bolts, stoppers, folding handle wire gauge, pipe rods etc
Glass fixer   13,000.00  
Truck/Suzuki rent   10,000.00 For Bath tiles loading, marble tiles, sanitary fittings like commode etc
Bath mirrors   10,000.00 Large glass
Fiber glass   28,000.00 for 2 open roof sections on 1st floor
Bhal/plants   10,000.00  
Graphiato   25,000.00 For exterior paint
contractor charges   600,000.00 House is ready in 6 months Sub totalRs 37,17,17 commencing from S.No 16
Basement cement   66, cement bags in basement size 15'x15' only cement included.
Basement labour charges   70,000.00 To be paid to labour contractor for work
Earthing   5,000.00 Done at the end for safety
3,792,717.00